Last year, one of our specialist HV teams supported the Dunmanway Wind Farm project in Ireland, delivering Irish 110kV cable jointing, terminations and testing for Suir Engineering to enable completion of the ICP‑approved connection.

Scope

The project scope included installation of 110kV XLPE cable joints to UK and Irish HV standards, along with joint bay construction and cable preparation.

We delivered straight joints and cross‑bonded configurations to support the long‑distance EHV circuit design, covering all stages from sheath preparation and conductor crimping through to insulation rebuild and stress control.

Full 110kV HV testing was completed, with comprehensive ICP documentation provided to enable Suir Engineering to finalise the connection.

Challenges

The project involved several notable challenges that shaped our delivery approach:

Approach

We applied a structured, quality‑driven approach to the delivery of the high‑voltage jointing works, ensuring compliance, safety and programme certainty throughout.

Outcome

Despite the complexity of the route and programme, the project was delivered to the highest technical and safety standards, achieving full compliance and a defect‑free handover.