Restoring Customer Confidence Through Precision Re-Delivery of a Three-Phase Supply Upgrade
Earlier this year our team successfully completed a complex supply upgrade installation project for Electricity Northwest (ENW), following a customer complaint arising from works previously carried out by another contractor. ENW engaged IES to take control of the project, rebuild trust, and ensure the installation was delivered to the highest professional standard.
Scope
After surveying the properties, it was clear that the project required a complete and carefully managed re-delivery of the supply upgrade, including:
- Full engagement with the initially dissatisfied customer and all affected neighbouring properties.
- Removal of historic, poorly secured and inappropriate cabling across the building.
- Safe disconnection of the original single-phase services.
- Installation of a new, compliant three-phase supply cable.
- Specialist traffic management planning due to restricted access.
Approach
Our approach blended technical precision with careful stakeholderconsultation:
- Direct engagement with the homeowner who raised theinitialcomplaint, buildingtransparency,and trust.
- Detailed planning to remove two original supply cables and four additional, incorrectly installed cables.
- Design of a bespoke traffic management solution, enabling safe works within a strict 15-minute closure window on a narrow, high-traffic road.
- Installation of a single, correctly fixed three-phase supply cable to replace the multiple legacy lines.
- Minimisingdisruption to local businesses,residents,and the nearby train station.
- Ensuring allworks weredelivered quickly,neatlyand professionally.
Challenges
The project presented several constraints thatrequiredinnovative solutions:
- Restricted Access: The properties sat on a narrow road heavily used by businesses and rail passengers; a full closure was not permitted.
- Traffic Management: Safe access could only be achieved through a precisely controlled 15-minute closure window, demanding tight coordination.
- Stakeholder Confidence:Previouscontractor failingshadcreated a lack oftrust, requiring consistent communication and reassurance to bring all property owners back on board.
Outcome
Despite the constraints, the project was delivered seamlessly and to the satisfaction of all stakeholders:
- Complete resolution of the original customer complaint.
- Removal of all six legacy cables and installation of a single, fully compliant three-phase supply.
- Safe and reliable electrical infrastructure supply for the properties.
- Enhanced long-term integrity of the installation and improved external appearance.
- Reinforced confidence from both ENW and the customer in the professionalism and quality ofthe service delivered fromIES.
“The work was done quickly, neatly and in a very professional manner. The difference between this crew and the last in terms of behaviour on site was like night and day – everyone was so considerate throughout.” – ENW Team.
Benefits
- Through a combination of technicalexpertise, carefulplanningand exceptional stakeholder care, ENWbenefitedfrom:
- Restoration of customer trust and full resolution of a complaint.
- A fully compliant, future-proofed three-phase supply installation.
- Minimisedcommunity disruption in a sensitive access location.
- Confidence that the project was delivered safely, neatly and to the highest professional standard.