Delivering Enhanced Network Control Through Pressure Monitor Valve Installation in Wirral

Challenge

  • Integrating new PMV equipment into an established network required accurate alignment to ensure optimal performance
  • Excavating and exposing the existing pipework demanded precision to prevent damage to the asset and surrounding infrastructure
  • Working on an existing live main required careful planning and controlled operations to ensure safety and avoid supply disruption

Solution

  • Undertook controlled mechanical excavation to safely expose the existing water main, ensuring accuracy and protection of the live asset
  • Installed the PMV system in line with approved designs, integrating it into the network with careful attention to alignment and performance requirements
  • Carried out full testing and commissioning to validate functionality and confirm successful operation of the system
  • Constructed a purpose-built chamber to house the PMV, providing long-term protection and safe access for maintenance
  • Completed full reinstatement works, leaving the site clean, safe and fully operational

Outcome

  • Successfully installed and commissioned the PMV system within the two-week programme
  • Enhanced pressure monitoring capability across the network, supporting improved operational control
  • Delivered all works safely and to a high standard of quality
  • Seamless integration with the existing network, with no issues during commissioning
  • Demonstrated efficient delivery of critical infrastructure upgrades within a constrained timeframe
Delivering Enhanced Network Control Through Pressure Monitor Valve Installation in Wirral

Project Location

Bebbington, Wirral

Client

United Utilities

Description

IES Utility Solutions were appointed as a contractor to install and commission a Pressure Monitor Valve (PMV) system on an existing water main in the Wirral. The works included controlled excavation, PMV installation, testing, and construction of a dedicated underground chamber.

Key Stats

  • Two weeks on site
  • Four person delivery team
  • PMV Installation

Project Delivered

April 2026