Project Location
Maltby, England
Client
Cadent Gas
Description
IES Utility Solutions delivered a full Above Ground Installation (AGI) capacity upgrade for Cadent Gas Networks within their East Midlands network in Maltby. The project addressed multiple undersized site assets through a comprehensive upgrade of PRS streams, outlet pipework, pre-heat systems and E&I infrastructure. Acting as Principal Contractor, IES managed design interpretation, construction, commissioning support, documentation and coordination across multidisciplinary subcontractors, delivering a complex programme within a constrained, high-risk site.
Key Stats
- Stopple operations delivered safely and effectively
- Full PRS stream rebuild including regulators, valves and pipework
- Pre-heat system upgrade including modular boilers, pumps, valves and heat exchangers
- E&I infrastructure installed including cabling, instrumentation and impulse lines