Case Studies

Complex Infrastructure Deconstruction in Lincoln for Cadent Gas

Challenge

  • Delivering works within a highly sensitive location, combining rail infrastructure and an environmentally significant canal corridor
  • Coordinating extensive pre-construction planning across multiple stakeholders
  • Securing approvals and permissions from key organisations, including Network Rail, the Environment Agency and the Canal & River Trust
  • Managing risk and ensuring compliance across safety, environmental and operational requirements prior to commencing on site

Solution

  • Undertook significant pre-construction collaboration to align technical, environmental and safety requirements across all stakeholders
  • Scheduled works during weekend evening periods to minimise disruption to surrounding infrastructure and operations
  • Established clearly defined work zones, access routes and safety controls to maintain a safe and controlled working environment
  • Engaged specialist subcontractor Taziker to support delivery of the deconstruction and removal works

Outcome

  • Successfully removed redundant infrastructure while protecting surrounding assets and the local environment
  • Demonstrated capability in delivering complex works within environmentally sensitive and infrastructure-constrained locations
  • Completed the project safely and within the agreed programme
  • Accelerated delivery, completing the 10-week programme in just 5 weeks
Complex Infrastructure Deconstruction in Lincoln for Cadent Gas

Project Location

Ferry Lane, Lincoln

Client

Cadent Gas

Description

IES Utility Solutions was engaged to deliver a complex gas infrastructure deconstruction and removal project spanning Network Rail lines and the environmentally sensitive Foss Dyke Canal corridor. The scheme required careful coordination and planning due to the combination of live infrastructure interfaces and environmental constraints, demonstrating the team’s ability to manage and deliver works in high-risk, regulated environments.

Key Stats

  • Infrastructure removal across rail and canal interfaces
  • Multi-stakeholder delivery including Network Rail, Environment Agency and Canal & River Trust
  • 10-week programme completed in 5 weeks

Project Delivered

March 2026 (10 week project completed in 5 weeks)

Get in touch

To talk to our project management team: