Ensuring Safety & Resilience at Stansted Airport Cargo Area

Challenge

  • Constant vehicle activity within a live cargo hub, with high volumes of HGV and service traffic
  • Working in an extremely traffic-sensitive environment, with large vehicles operating in confined spaces adjacent to critical gas assets
  • Limited operational windows and controlled access due to the presence of numerous underground services
  • Maintaining safe conditions for both airport personnel and site teams throughout the works
  • Meeting stringent Department for Transport (DfT) and UK Roads Liaison Group (UKRLG) standards

Solution

  • Conducted a detailed risk assessment aligned with DfT guidance and UKRLG standards to determine the most appropriate VRS solution
  • Engaged early with Cadent Gas, design partners and airport authorities to address safety, access and technical requirements
  • Developed a phased construction and traffic management plan to maintain safe working zones and minimise disruption to cargo operations
  • Implemented regular briefings, close supervision and coordinated scheduling to support safe and efficient delivery in a constrained environment
  • Installed eight heavy-duty safety bollards around the existing gas governor to protect critical infrastructure from potential vehicle impact

Outcome

  • Successfully delivered the project safely and ahead of schedule
  • Provided robust, long-term protection for critical gas infrastructure, reducing operational risk
  • Ensured full compliance with industry standards and airport operational requirements
  • Completed all works with zero disruption to day-to-day airport activities
Ensuring Safety & Resilience at Stansted Airport Cargo Area

Project Location

Stansted Airport Cargo Area, Essex

Client

Cadent Gas

Description

IES Utility Solutions successfully delivered a full design-and-build VRS solution for Cadent Gas within the busy Stansted Airport cargo area. With continuous HGV and service vehicle movements, the project demanded a highly planned, safety led approach to protect existing gas infrastructure and maintain airport operations. Working in such a traffic sensitive environment required careful sequencing and close engagement with airport stakeholders from early design through to final installation. This project demonstrated IES Utility Solution’s capability to deliver complex safety-critical projects in high pressure environments.

Key Stats

  • Design-and-build VRS solution delivered
  • Eight Heavy duty safety bollards installed
  • Delivered within a live, high traffic airport cargo environment

Project Delivered

March 2026