Case Studies

Delivering Trenchless Solutions for Complex Mains Rehabilitation

Challenge

  • Persistent wet weather throughout the full six-week programme, with rainfall experienced every day, significantly impacting ground conditions and excavation activities
  • Saturated terrain across farmland and rural routes, increasing the risk of access issues and plant becoming immobilised
  • A disused railway line running above sections of the main, creating additional constraints around access, ground stability and design approvals
  • Unforeseen challenges encountered along the route, requiring reassessment and redesign of elements of the project, leading to minor delays while solutions were agreed

Solution

  • Installed track mats from key access points across fields and rural terrain, enabling safe and continuous movement of plant and vehicles while minimising land damage
  • Adapted excavation processes by transferring excavated material directly into grab wagons, reducing the risk of soil being displaced or washed across the site due to heavy rainfall
  • Deployed a specialist 15-tonne long-reach machine to safely access and complete works in the constrained areas around the disused railway line
  • Progressed works in controlled 110-metre sections, allowing installation and connection to continue while design adjustments were made elsewhere on the route

Outcome

  • Completed the project ahead of programme despite sustained adverse weather conditions
  • Successfully reinstated all water services, restoring the main to full operational performance
  • Delivered high-quality installation supported by rigorous testing and validation in line with client and industry standards
  • Ensured long-term reliability and integrity of the rehabilitated asset prior to final handover
  • Maintained efficient delivery through adaptive planning and on-site problem solving
Delivering Trenchless Solutions for Complex Mains Rehabilitation

Project Location

Arlecdon, Cumbria

Client

United Utilities

Description

IES Utility Solutions delivered a mains rehabilitation project in Cumbria, as principal contractor, using the trenchless method of pipe insertion for 1.4km water mains. Completed over the course of 6 weeks the team worked through strong wet weather conditions along the mains across fields, country lanes and farmland. The project involved rehabilitating a 10 inch water main by installing a 160mm PE liner along the full length of the affected network, including associated preparation, insertion and reinstatement activities required to return the asset to service.

Key Stats

  • 1467metres of mains replaced using the trenchless method of pipe insertion

Project Delivered

January – February 2026

Get in touch

To talk to our project management team: